*|MC:SUBJECT|*

View this email in your browser

Shift Program Construction Update

November 2019

With new construction on the horizon, the Shift program is dedicated to providing you with up-to-date information about the major projects bringing new amenities and resources to your neighborhood. Please note, construction schedules are subject to change. To confirm the information below and other work schedules, contact Shift at 844-SHIFT-SD.

Visit ShiftSanDiego.com or follow @ShiftSanDiego on Twitter for continuous updates on construction information that may impact your neighborhood.

 

Mid-Coast Trolley Construction, SANDAG Project

Genesee Avenue
The last concrete deck pour along Genesee Avenue was completed on November 14. Concrete work will continue over the next several weeks but on a smaller scale. Crews will begin to remove falsework, the temporary framework used to support a structure during its construction, from the viaduct near Nobel Drive after the winter holidays. Falsework will be fully removed, except for at the Trolley stations, by the end of March 2020. Overall construction in this area will continue over the next year.

Voigt Drive
Work has begun on a project to realign the intersection of Campus Point Drive and Voigt Drive and to widen Voigt Drive to accommodate the future Trolley station. Construction impacts in this area will continue through the next several weeks and will include intermittent nighttime closures on Voigt Drive to allow for utility work, restriping, setting k-rail (concrete barriers) and other construction activities.

Nobel Drive
Nightly closures of Nobel Drive began on December 8 to remove falsework from the Trolley bridge over Nobel Drive and to remove k-rail from the site. Closures are scheduled to take place December 8–10, from 10 p.m. to 5 a.m. each night.

Trolley Overcrossing south of Nobel Drive
On November 18, Mid-Coast Trolley crews conducted a concrete deck pour along the overcrossing south of Nobel Drive, where the Trolley bridge crosses over Interstate 5 (I-5). Falsework is anticipated to be removed in February 2020 and will require freeway closures. More information will be provided once dates are confirmed. Visit the SANDAG YouTube channel to view a video of the recently completed deck pour.

Mid-Coast Trolley crews pour concrete along the Trolley overcrossing south of Nobel Drive
For more information on the Mid-Coast Trolley project, including a map, detours and what to expect, visit KeepSanDiegoMoving.com/MidCoastTrolley, Facebook.com/MidCoastTrolley or @ShiftSanDiego on Twitter.
 

Rose Canyon Bike Path, SANDAG Project 

A full closure of the Rose Canyon Bike Path began on the morning of Tuesday, December 9 for crews to pave the final section of the new path. The bike path is expected to reopen by 6 p.m. on Friday, December 13. During the closure, a bicycle-carrying shuttle service will be in operation from 5 a.m. to 8 p.m. daily to transport cyclists and pedestrians around the work area. The closure was initially scheduled to begin on November 19 but was postponed twice due to forecasted inclement weather. Please check KeepSanDiegoMoving.com/MidCoastNotices or follow us on Twitter @ShiftSanDiego for the latest information.

A south-facing view of a completed section of the new and improved Rose Canyon Bike Path
 

I-5/Genesee Avenue Interchange, SANDAG and Caltrans Project 

The I-5/Genesee Avenue Interchange Project is a joint project between SANDAG and Caltrans. In recent weeks, ramp meters were activated at the northbound and southbound I-5 on-ramps from Genesee Avenue and the southbound on-ramp from Roselle Street. Traffic operations engineers have modified the northbound on-ramp meter at Genesee Avenue to operate Monday through Friday, from 6 to 7 p.m. to minimize traffic back-up. Over the coming weeks, Caltrans will continue to evaluate and adjust the meters at all I-5/Genesee Avenue Interchange freeway ramps. The activation of the ramp meters is part of the final set of completion tasks associated with the I-5/Genesee Avenue Interchange Project.

An aerial view of the completed I-5/Genesee Avenue Interchange, facing southwest
 

North Torrey Pines Living and Learning Neighborhood, UC San Diego Project 

Traffic signal and sidewalk construction at the intersection of North Torrey Pines Road and Muir College Drive is targeted to begin in mid-December, after UC San Diego’s fall quarter is complete, and will continue for approximately two weeks after work has begun. In addition, a new right-hand-only turn lane from Genesee onto southbound North Torrey Pines Road will be added to the intersection. Timing is TBD. The water line connection on the northbound lanes of North Torrey Pines Road will require closures. Timing is TBD and will require approximately one week of night work. Two academic towers, buildings 1 and 2, will be topping out this month. Cranes from two residential towers, buildings 3 and 4, will be coming down this month.

Work continues on the UC San Diego campus
 
Let us know what projects you’re most interested in receiving information about via email at info@ShiftSanDiego.com or phone at 1-844-SHIFT-SD. Visit ShiftSanDiego.com to sign up for email alerts about major construction updates and access the map of all the ongoing projects.
 
The Shift San Diego Team
 

For information about this work and other construction schedules call Shift at 844-SHIFT-SD. For additional information about the Mid-Coast Trolley project call (877) 379-0110, email midcoast@sandag.org, or visit KeepSanDiegoMoving.com/MidCoast.

Si desea obtener información en español, por favor comuníquese al (619) 699-1950 o pio@sandag.org.

In compliance with the Americans with Disabilities Act (ADA), this document is available in alternate formats by contacting the SANDAG ADA Coordinator, the Director of Administration, at (619) 699-1900 or (619) 699 -1904 (TTY).

About Shift

The Shift program, formed by the San Diego Association of Governments, is designed to provide residents, businesses and commuters impacted by construction in University City and La Jolla with information and resources to minimize disruption, confusion and potential traffic challenges, as well as provide transportation solutions. For more information, visit ShiftSanDiego.com. To view other possible closures or impacts in the area, visit the construction notices section of Shift. Sign up for text alerts to receive notices for major construction and impacts by texting “ShiftSD” to 797979 and check out Shift’s commuter resources to help you get around the construction.

 
Copyright © *|CURRENT_YEAR|* *|LIST:COMPANY|*, All rights reserved.
*|IFNOT:ARCHIVE_PAGE|* *|LIST:DESCRIPTION|*

Our mailing address is:
*|HTML:LIST_ADDRESS_HTML|* *|END:IF|*

Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.

*|IF:REWARDS|* *|HTML:REWARDS|* *|END:IF|*